Why so much money? From my past recollection of 3 yrs. ago, NEOSD advised that fixing the dam & watershed issue at Horseshoe Lake would cost $6M. As part of that discussion, (CONTINUED)

Complete Question: Why so much money? From my past recollection  of 3 yrs. ago, NEOSD advised that fixing the dam & watershed issue at Horseshoe Lake would cost $6M. As part of that discussion, NEOSD would pick up the tab. Now, with a drained lake, NEOSD states that the cost of fixing the dam would be in excess of $21M. AND, even though Customers in NEO have been paying 3-times what was assessed prior to ‘Save the Watershed’, we [Shaker Hts & Cle Hts] are told that “you [S.H. & C.H.] need to pick up the

Answer: The initial estimate involved repairs to the existing spillway and the installation of overtopping protection. The worsening dam conditions around the spillway caused a reassessment that dam reconstruction or dam removal were the only options to ensure public health and safety. As part of the reassessment, sediment testing and analysis indicated the need for extensive sediment handling and removal to facilitate either dam reconstruction or dam removal.

Show All Answers

1. Will you file an environmental impact statement?
2. Residents rely on the trails surrounding Horseshoe Park for fitness and transportation. Breaking the loop around the park by eliminating the dam and spillway...(CONTINUED)
3. Past circumstances led Horseshoe Lake to be classified as a Class 1 dam. Given NEORSD’s reworking of the Lower Lake dam, if non NEORSD funds are raised to pay for it, can...(CONTINUED)
4. When NEORSD calculated Horseshoe Lake rebuilding at $20.7 million, how many acre feet of storage volume were in that plan (for Horseshoe Lake) and at what average depth?
5. Are there any federal funds that could be applied for to pay for the additional cost of repairing or recreating the horseshoe lake dam?
6. NEORSD cited cost for Horseshoe of $6 mil, then $20 mil in a clarification response; then Cleveland.com story cites $30 mil. We need independent cost assessment. (CONTINUED)
7. Why so much money? From my past recollection of 3 yrs. ago, NEOSD advised that fixing the dam & watershed issue at Horseshoe Lake would cost $6M. As part of that discussion, (CONTINUED)
8. If the horsehoe Lake is eliminated, will the new dam at the lower lake have to be gigantic in order to handle the water from the Horse Lake area, (CONTINUED)
9. The Shaker Lakes represent far more to our community than a means of flood control. They are a place of community, a wildlife refuge, an important historical location, and much more. (CONTINUED)
10. Since boating, swimming and fishing are going to be permitted in Lower Lake, the fleeing nesting and breeding wildlife that need a lake environment will need a protected refuge; (CONTINUED)
11. If NEORSD removes Horseshoe dam and Lake, then the resulting new dam at Lower Lake will need to be much larger, destroying the beauty and historical...(CONTINUED)
12. How can we let Horseshoe lake disappear! Maybe the Sewer district says the lake isn't worth fixing but do they live here? Do they realize what...(CONTINUED)
13. Was heavy machinery used to on the bridge and deck at Horseshoe Lake dam for recent parapet work and could that have contributed to further and more drastic deterioration...(CONTINUED)
14. In the early going shortly after Horseshoe Lake was drained, could earth-moving equipment have been brought in (from North Park or South Park or the park itself)...(CONTINUED)