Project 15-36, Amendment: E. Netzel-Hatcher, 1450 & 1474 Rydalmount (PPN 684-36-005 & 684-36-027),
‘MF-1’ Multi-family, requests lot joining.
Approved amendment to prior approval, 7-0, with the following conditions:
- The newly created lot shall not include any Mayfield Road and Rydalmount Road right-of-way; and
- Prior to submitting the plat to the County Recorder, it must be signed by the Director of Law and Director of Planning & Development.
Project 16-2: J & M Meilstrup, dba CrossFit I/O, 2086 S. Taylor Rd.,
‘C-2’ Local Retail, request cond. use permit to operate CrossFit gym per Code ch. 1111, 1115, 1131, 1151, 1153, & 1161.
Approved, 7-0, with the following conditions:
- That the use will not be injurious to the use and enjoyment of other property in the immediate vicinity or create a nuisance for nearby businesses;
- The applicant shall work with staff to resolve any complaints from neighbors; and
- The installation of the use shall be completed within 18 months of Planning Commission approval.
Project 16-3: Forest Hill Kitchen, LLC, 3099 Mayfield Rd.,
‘C-2’ Local Retail, requests cond. use permit to operate catering & meeting room, banquet hall, party center per Code ch. 1111, 1115, 1131, 1151, 1153 & 1161.
Catering Approved, 7-0, with the following conditions:
- The use will not be injurious to the use and enjoyment of other property in the immediate vicinity or create a nuisance for adjacent residential properties;
- The applicant shall work with staff to resolve any complaints from neighbors; and
- The installation of the use shall be completed within 18 months of Planning Commission approval.
Meeting Room/Banquet Hall/Party Center Approved, 7-0, with the following conditions
- The use will not be injurious to the use and enjoyment of other property in the immediate vicinity or create a nuisance for adjacent residential properties;
- The applicant shall work with staff to resolve any complaints from neighbors; and
- The installation of the use shall be completed within 18 months of Planning Commission approval.
Project 16-5: Hebrew Academy of Cleveland, 1516 Warrensville Center Rd.,
‘AA’ Single Family, requests cond. use permit to operate high school & administrative offices in former Oakwood Club clubhouse, retain & reuse outbuildings & construct play fields/courts per Code ch. 1111, 1115, 1121, 1151, 1153, 1161, 1165, & 1166.
Approved, 6-0-1, with the following conditions:
- Architectural Board of Review approval for new front yard fencing and signage;
- Final signage, landscaping, grading, tree preservation and drainage plan shall be approved by the Planning Director by April 1, 2016. Required landscaping must be installed within 90 days of high school opening;
- Applicant shall discourage cut-through traffic, including through signage, and facilitate drivers’, pedestrians’ and bicyclists’ movements through the site;
- The use will not be injurious to the use and enjoyment of other property in the immediate vicinity or create a nuisance for adjacent residential properties;
- The applicant shall work with staff to resolve complaints from neighbors;
- Receipt of all required Building Department permits; and
- The installation of the use shall be completed within 18 months of Planning Commission approval.